Dunara
A wide view of marram-grassed dunes with scattered umbrella pines, the Atlantic beyond, in low golden light.

Measured, then published

Nine figures, and which of them are targets

A resort on a dune in the Alentejo has two hard constraints: water in July and sand that moves. Everything on this page is one of those two problems, the plant that answers it, and the meter that says whether the answer worked.

Dune under restoration
11.4 ha
Own generation
756 kWp
Irrigation from recycled water
41%
First full reporting year
2026

The method

Metered, not asserted

2026 is the first calendar year in which the whole estate was open. These are its numbers.

Every figure below comes off a meter, a weighbridge ticket, a delivery note or a survey, and each one names where it comes from. Where a number is a target rather than a reading, it says target. That distinction is the only thing that makes the rest of the page worth reading.

Two figures are already uncomfortable and are printed anyway: waste diverted from landfill, which came in at 71% against an 85% target, and the share of planted ground still on irrigation. Both are in the published set with the arithmetic behind them.

The set is published each March for the previous calendar year. Phase 3 adds four villas in 2027 and Phase 4 adds twenty-four houses by 2028, so the per-guest figures will move and the restated series will show it rather than quietly rebasing.

214 l
water drawn per guest-night, 2026
56%
of electricity used came off our own roofs
11.4 ha
of dune replanted by hand since 2023
68%
of produce by weight from within 60 km
A shallow black-bottomed reflecting pool in a plaster courtyard, the colonnade mirrored in still water.

Water

Two boreholes, and everything else used twice

There is no mains water here. Two boreholes, drilled to 112 metres in August and October 2023, supply the whole estate; abstraction is metered and reported monthly, and the estate drew 58 400 m³ in 2026. Divided by occupied keys that is 214 litres a guest-night, against a target of 180 by 2028.

Greywater from all 88 keys and from the spa is treated in a plant behind the earth bund and returned to irrigation — 31 200 m³ of it in 2026, which covered 41% of what the planting drank. Pool backwash is not discharged: it settles, is filtered and goes to the same irrigation ring, adding 2 100 m³ a year. Rainwater off 1 900 m² of hard standing runs to a 340 m³ tank and contributes about 1 100 m³.

The nine bodies of water hold 2 155 m³ across 1 715 m² of surface, and that surface evaporates roughly 7 900 m³ a year on this coast. Thermal covers go on the lap pool and the children's pool between 23:00 and 07:00 and take about 2 200 m³ of that back — the single largest water saving on the estate, from two covers and a timer.

Boreholes
2, to 112 m
Drawn, 2026
58 400 m³
Greywater returned
31 200 m³
Backwash reclaimed
2 100 m³

Water, as operated

The water balance

MeasureFigureSource
Abstraction, 202658 400 m³Borehole meters, read monthly
Per guest-night214 lAbstraction divided by occupied keys
Greywater treated and reused31 200 m³Treated-water meter at the plant
Share of irrigation from recycled water41%Irrigation ring meters
Pool backwash reclaimed2 100 m³ a yearSettlement tank meter
Rainwater harvestedabout 1 100 m³ a year340 m³ tank, level logger
Water surface and volume1 715 m² · 2 155 m³As-built record
Evaporation from that surfaceabout 7 900 m³ a yearMake-up meter, net of backwash
Saved by night coversabout 2 200 m³ a yearMake-up meter, covered against uncovered nights
Pool turnover4 hoursPlant-room design, verified at commissioning
Irrigation window03:30–06:00, drip onlyController log, 22 stations
Potable water used on the dune itself0 litresThe restoration is rain-fed by design
Planted ground taken off irrigation6.2 of 9.1 haController log; a zone comes off after its third summer

Irrigation runs at night because drip emitters lose a measurable fraction of their output to evaporation in Alentejo afternoon air, not because it is tidier. The 22 stations are driven by soil-moisture probes, so a wet week costs nothing to notice.

Steam rising off a warm outdoor thermal pool into cold dawn air, dark stone coping, plaster wall behind.

Energy

The building does most of it before the plant starts

The pavilions sit on an axis 28° west of south, which is not the prettiest orientation and is the right one: the 3.40 m loggia shades the full height of the glass from 1 May to 12 September between 11:00 and 17:00, and lets the low winter sun straight onto the floor slab. That slab and the 300 mm walls give a decrement delay of about 11 hours, so a room carries the night's cool into the middle of the afternoon.

High-level openings on both sides of every pavilion are driven by the building management between 23:00 and 06:00 whenever the outside air is 4 K below the inside. In the three months to September 2026 that purge did the cooling on 58 nights without the compressors running at all.

What is left is electric. Four water-to-water heat pumps on the borehole return give 1 240 kW thermal at a measured COP of 4.6 on pool duty and 3.8 on domestic hot water. Heat recovery in all 88 keys runs at 86% sensible efficiency and clawed back 318 MWh in 2026.

Generation is 1 644 photovoltaic panels at 460 W — 756 kWp — on the service yard and the vehicle canopies, with 1 200 kWh of battery storage. None of it is on a planted roof: the roofs are the reason the estate cannot be seen from the ridge, and that was not for sale.

Array
756 kWp, 1 644 panels
Storage
1 200 kWh
Heat pumps
1 240 kW, COP 4.6
Heat recovery
86% sensible

Energy, as operated

Where the electricity came from in 2026

MeasureFigureSource
Consumed by the estate1 878 MWhIncoming meters
Generated on site1 164 MWhInverter logs
Generated and used on site1 046 MWhInverter and incoming meters, netted
Share of consumption self-generated56%1 046 of 1 878 MWh
Exported to the grid118 MWhExport meter
Target self-generated share, 202875% (target)Second array, 310 kWp over the Phase 3 and 4 canopies
Array756 kWp · 1 644 panels at 460 WAs-built record
Battery1 200 kWh, discharging to 600 kWAs-built record
Heat pumps4 units, 1 240 kW thermalAs-built record
Measured COP, pool duty4.6Plant-room heat and electricity meters
Measured COP, domestic hot water3.8Plant-room heat and electricity meters
Heat recovered by ventilation318 MWhMVHR duct sensors, 88 keys
Nights cooled by purge alone58 of 92, July–September 2026Building management log
Colour temperature on the estate2 700 K, nothing above 3 000 KLighting schedule
Illuminance at the dune crest, new moon0.4 luxMeter at three fixed points

Every service on the estate is electric, which is why one number — the self-generated share — answers for the whole carbon question rather than being one line of several. The 2028 target depends on a second array over the Phase 3 and Phase 4 canopies, which is consented and not yet installed.

A sand path through umbrella pines, dappled light on the ground, cistus and rosemary at the edges.

The dune

Five kilometres of moving ground

The dune ridge between the estate and the Atlantic is about 5 kilometres long, and 11.4 hectares of it fall inside the boundary. It is the one part of the site that is alive in the engineering sense: it moves, it loses its crest to a winter storm and it rebuilds if the marram holds.

So the restoration began in November 2023, before the first pavilion, and it is the only line on the construction programme that runs past the last phase. 184 000 marram plants have gone in by hand over five seasons, with 2 400 metres of chestnut sand fencing in fourteen runs set across the prevailing north-westerly to catch sand and hold it where the crest wants to be.

Every walk to the beach goes over one of seven boardwalk crossings — 1 180 metres of decking, milled from the same maritime pine boards that shuttered the concrete. Eighteen fixed transects are surveyed twice a year; across their mean the crest stands 0.34 metres higher than at the first survey in 2023, against a target of 0.60 metres by 2028.

Of the 1 900 pines surveyed before a line was drawn on this site, 1 889 stand today; the eleven taken out for the access spur are in the bar counter and the reception joinery. 240 young pines have gone in to close the age gap in the stand.

Dune in the boundary
11.4 ha
Marram planted
184 000
Sand fencing
2 400 m
Crest gain since 2023
0.34 m

Ground and planting

What is growing, and where it came from

MeasureFigureSource
Estate47 haTitle plan
Dune under restoration11.4 haSurvey
Pine woodland retained1 889 of 1 900 surveyed treesTree survey 2022, re-walked 2026
Pines planted240Planting record
Pines removed11, for the access spurConsent discharge; milled into the bar and reception joinery
Marram planted by hand184 000 over five seasonsPlanting record
Chestnut sand fencing2 400 m in 14 runsAs-built record
Boardwalk crossings to the beach7 crossings · 1 180 m of deckingAs-built record
Planted roof3 840 m², 11 speciesAs-built record
Species across the estate34, all propagated within 60 kmNursery delivery notes
Shrubs planted6 800 — cistus, lavender, rosemary, juniper, thriftPlanting record
Dune monitoring18 fixed transects, surveyed twice a yearSurvey file, 2023 onward
Crest level, mean of transects0.34 m above the 2023 baselineSurvey file
Target crest level, 20280.60 m above baseline (target)Restoration programme

Marram is planted by hand because a machine compacts the sand it is trying to stabilise. Five seasons of twelve people with dibbers is the whole technology, and it is the reason the crest is higher than when we arrived.

Waste, in seven streams

Glass, metal, paper and card, plastics, organics, cooking oil, and bulky or construction waste. Seven bins behind every kitchen and every housekeeping station, weighed at the service yard, with the weighbridge tickets kept because a diversion rate nobody can audit is a slogan.

In 2026, 71% of the estate's waste was diverted from landfill against a target of 85% by 2028. The gap is almost entirely mixed plastics and the back end of Phase 3 construction, and both are named in the published set rather than averaged away.

14.2 tonnes of food waste was composted on the estate and went back into the planting. 3 100 litres of cooking oil left for processing. Linen is held in eleven grades and repaired on site; 2.4 tonnes reached the end of that cycle and was cut down for rags rather than replaced wholesale.

Guest rooms have no single-use plastic bottles because the estate's water is treated to drink and supplied in returnable glass from the LUMAR bottling bench — 36 200 litres of it in 2026, filled and washed 1.2 km from where it is poured.

Food, and how far it travelled

68% of produce by weight came from within 60 kilometres in 2026, and 91% from within Portugal. The figure is taken off delivery notes rather than estimated, which is why it is 68 and not 70.

Fish is bought off the Sines and Setúbal fleets, two to seven landings a week depending on the swell, and the boards at BRASA and MIRANTE are written after the fish arrives rather than before. When the Atlantic closes for a week, the menu says so.

The kitchen garden runs to 0.8 hectares at the north of the estate, 41 varieties, and supplies the market table at A CASA from May to October. Beef and lamb come from two Alentejo producers inside 40 kilometres. All of the bread, pastry and chocolate is made in the LUMAR bread room.

The cellar holds 640 references, of which 402 are Portuguese and 118 come from the Alentejo and the Península de Setúbal. That is a sourcing decision as much as a list: the shortest supply line in the building is also the one the sommelier can walk.

The published set

Nine figures, every March

The 2026 column is measured. The 2028 column is a target and is labelled as one. Every figure traces to our own meter, ticket, delivery note or survey, and the fourth column says which — printed at this level of detail so that it can be argued with.

Figure2026, measured2028, targetHow it is measured
Water drawn per guest-night214 l180 lBorehole meters divided by occupied keys
Irrigation supplied from recycled water41%60%Treated-water and irrigation ring meters
Electricity used that the estate generated56%75%Inverter logs against incoming meters
Heat-pump COP at pool duty4.64.8Plant-room heat and electricity meters
Waste diverted from landfill71%85%Weighbridge tickets, seven streams
Produce from within 60 km, by weight68%75%Delivery notes, audited quarterly
Planted ground off irrigation6.2 of 9.1 ha9.1 of 9.1 haIrrigation controller log
Dune crest above the 2023 baseline0.34 m0.60 m18 fixed transects, surveyed twice a year
Illuminance at the dune crest, new moon0.4 lux0.4 lux or lowerMeter at three fixed points

Published each March for the previous calendar year, with the earlier years restated beside it. 2026 is the first full year the whole estate was open; Phase 3 adds four villas in 2027 and Phase 4 adds twenty-four houses by 2028, and the per-guest figures will move when they do.

A high view of low flat-roofed pavilions among pines and dunes, water terraces between them.

The construction file behind every figure on this page

The boreholes, the heat-pump ring, the 410 mm roof build-up and the programme that put the dune restoration ahead of the first pavilion are all published, with the trades who did the work credited by discipline.